Concrete Batching Plant
Virginia QLD
October 2009 - Jan 2010

 

Scope: Our client had a factory fire in September 2009. After installing emergency temporary power and communications for our client, our task was to re-instate the batching plant into pre-incident condition. This included re-wiring the entire plant, repair/replace all electrical components on the plant as required. Carry out full commissioning of the plant. In addition we re-wired the entire factory lighting and power systems.

Project Value: $144,000

 



Commercial Office
Geebung QLD
November 2009

 

Scope: Our client relocated their head office and warehouse. Our task was to install power outlets and communications for their 30+ office staff. We also supplied and installed a UPS on the main server.
In addition, we installed 79 safety switches in the warehouse/offices and inspected the emergency lighting system.

Project Value: $29,700

 

Commercial Kitchen
Heathwood QLD
October 2009

 

Scope: Our client anticipated an increase in sales for Christmas 2009 and required a temporary commercial kitchen setup in a short timeframe. Our task was to wire and install power outlets, lighting and communications for the commercial kitchen. Included was the repairs to a number of existing commercial kitchen equipment and the supply and installation and a new commercial electric oven.

Project Value $57,800 



Printing Frim

Tingalpa QLD
Janurary 2009

 

Scope: Our client required general lighing and power outlets in their new printing room. The job included 180 flourescent light fittings, 3 phase outlets for the print machines, and a switchboard upgrade. 

Project Value $26,600